projects

Filter on: Show all Customization Hall construction Stairs and Fences Steel construction

Expansion Phoenix Zevenaar

The Phoenix Zevenaar expansion is already taking shape. A beautiful construction of approximately 70 tons, built in phases. The floors were also laid. All work in perfect collaboration with Welling Bouw Didam. The work will be completed in the 1st week of January 2022.

read more
steel-construction

Kiel am Alten Bootshafen

In Kiel am Alten Bootshafen, all the balconies of building 4 have been mounted on the facade and Innenhof and the aligning of the balconies has started. Week 43 we will start with the balconies in Innenhof building 1 (shown in green). We expect an installation time of approximately 2 weeks. We will then continue

read more
stairs-and-fences

Progress phase 1 Kiel am Alten Bootshafen

At the construction site in Kiel, we are now fully assembling the last of the Innenhof balcony fences. We will then install the parapet gates on the 5th and 6th floors. Our goal is to be ready by week 49/50 with the installation of the last Loggia fencing.

read more
stairs-and-fences

AIM Markgröningen

In Markgröningen we had to install 2 front roofs with a span of the beams of 15 meters. It was quite a challenge to connect the 15 meter long tie rods at the right angle to the 4.8 ton HEM 650 girders. Together with the help of 2 mobile cranes, our Imetaal mechanics had to

read more

Qurios Resort Gulpen

Monday, October 26, we delivered and assembled the construction for the reception building of Qurios Vakantieresort in Gulpen. After the wide slabs have been laid and poured, the roof construction is assembled.

read more
steel-construction

Progress phase 1 Baumarkt Hornbach Enschede

In Enschede, the Baumarkt is really taking shape and we are steadily building. The nets are now also hanging so that the roof plates can be mounted.

read more
steel-construction

Baumarkt Hornbach Enschede

Week 17 we started with the assembly Baumarkt Hornbach in Enschede. It’s already starting to take shape.

read more
steel-construction

New production hall in Rottendorf

Construction of a warehouse for a pharmaceutical company in Ennigerloh. The substructure is built with an AT6 crane on the roof by the technical installation. Subsequently, the grating will be laid and the assembly will be completed for purchase.

read more
steel-construction

Ringers factory Alkmaar

Together with our client, we are renovating/conversion of the monumental Ringers factory in Alkmaar. Various substructures, new steel structures have already been installed. We are currently working on the assembly Construction Optopping. The spiral staircase has now been built in and despite the fact that it is being installed in an existing building, the steel

read more
steel-construction

Urban Oasis Ulft

The Urban Oasis is the prototype for a city park of 300 square meters in which innovative technologies make the environment cleaner and more sustainable. The aim is to improve the quality of life in cities. A project that will be scaled up internationally. A start has been made on the first Urban Oasis at

read more
customization steel-construction

Steel construction Ter Horst Varsseveld

Monday 19 October we started the assembly of the steel construction for the new hall for Ter Horst Metaaltechniek. We expect to have the assembly of the hall ready by the end of week 44. We will then start assembling the office.

read more
steel-construction

Friedenauer Höhe Berlin

Update Friedenauer Hohe Berlin The balcony and roof terrace fencing has been installed. In week 42 we will start with the privacy screens BT1. It is expected that we can start installing privacy screens and balcony railing BT2 at the end of November.

read more
stairs-and-fences

Toom Bochum fase 2

In week 26 we started assembling the steel construction Toom in Bochum. In 4 weeks, 271 tons of steel were installed, a best performance for the installation team. At the end of week 30, the assembly of the Windfang was completed with a total of 30 tons of steel. The Windfang also has a bakery

read more
steel-construction

AH Meijhorst

In week 38 we started assembling the steel construction AH plan Meijhorst in Nijmegen. Friday, September 18, the first part of the AH steel construction was completed to the satisfaction of the contractor. In week 42 we will start on plan Meijhorst with the assembly of the Lidl steel construction, and the pent and 1st

read more
steel-construction

Outdoor staircase Darmstadt

On Monday we completed the assembly of the 1st outdoor staircase 4.2 in Darmstadt. The assembly of the 2nd outside staircase type 2.2 may start in week 9.

read more
stairs-and-fences

Parkhaus Edeka Moers Fase 5

Progress Parkhaus Moers until wk 26 This week, the access and exit ramps for the 8th floor will be completed at Parkhaus Moers. The beams from axis 22 to 42 are then mounted. The beams are expected to be installed on Wednesday 1 July.

read more

Parkhaus Edeka Moers Fase 4

Progress Parkhaus Moers until wk 21 We are now fully engaged in the assembly of beams, tubes and drive-on mats on the 6th floor. By the end of this week we expect to be ready with this floor on axis 42 and are slightly ahead of schedule. However, we will need this lead with the

read more
steel-construction

Parkhaus Edeka Moers Fase 3

Week 19 2020 we have assembled the 5th floor of axis 1 to 21 and we will have this part of the assembly ready on Friday 8 May. Some of the beams have also been mounted between axis 22 and 42 and we will be assembling everything on the 5th floor in week 20.

read more
steel-construction

New construction Boels rental center Norderstedt

New construction Boels rental center Norderstedt Imetaal Stahlbau GmbH has again performed a wide variety of services for this construction project, such as: – Manufacture and assembly of a custom-made steel hall including concrete plinths and an industrial floor slab with leveling of the surface – Complete delivery and assembly of the foundations – Complete

read more
steel-construction

Lidl Lochem

Tuesday, April 14, we started assembling the steel construction for Lidl in Lochem. We expect to finish the crane work on Saturday the 18th. The bolt connections will be checked in week 17 and the assembly will also be completed.

read more
steel-construction

Parkhaus Edeka Moers Fase 2

Progress Parkhaus Moers until April 11 Due to the German holiday Karfreitag, it was not possible to work on the Parkhaus in Moers on Friday 10 April. On Saturday afternoon, April 11, the assembly was completed from Axis H to Axis A (axis 21 to 42).

read more
steel-construction

Parkhaus Edeka Moers Fase 1

Here some pictures of the assembly stand until wk 14 Parkhaus Edeka Moers In week 15 the assembly axis H / A (axis 21 to 42) will be ready. We will also start finalizing the 3rd floor. Due to Good Friday, construction will also be mounted on Saturday 11 April.

read more
steel-construction

Skoda & Opel Brass Dietzenbach

In week 13 we started with the installation of the first two parts at Skoda & Opel Brass in Dietzenbach. We expect to have the third part of Hall 1 ready by the end of week 14.

read more
steel-construction

Parkhaus Edeka Moers

In week 10 we started preparations for the installation of the Parkhaus Edeka in Moers. The first 4 loads were delivered on construction. All columns are now standing and the tubes are placed between the columns.

read more
steel-construction

Van Kimmenade Helmond

In week 7 we started assembling the Van Kimmenade office in Helmond. The temporary construction and construction of the first floor is now complete by the assembly team.

read more

Rudolf Steiner College Haarlem

In week 22 we started with placing the mounting columns for the Rudolf Steiner College in Haarlem. The first floor is already there. In the meantime, we started installing THQ beams on the second floor in week 27. This week the remaining steel and columns for the third floor will be mounted. After the holidays,

read more
steel-construction

Toom in Bochum

In week 26 we started with the installation of Toom in Bochum. We expect to have the assembly ready in week 29.

read more
steel-construction

Outdoor staircase Darmstadt

In week 5 we completed the assembly of the 1st outdoor staircase 4.2 in Darmstadt. The installation of the 2nd outdoor staircase type 2.2 may start in week 9

read more
stairs-and-fences

VB Airsuspension

Progress VB Airsuspension The steel construction is in the final phase. We hope to be able to complete the project at the end of January

read more
steel-construction

La Vie Berlijn

To guarantee the continuity of production and delivery, as well as the quality of the fencing for this work, a permanent production team has been appointed who has focused on the manufacture of these fencing. The team produced this assignment in a specially equipped workshop separate from our normal production area. At this large construction

read more
stairs-and-fences

Lidl Eibergen

Commissioned by Ten Brinke Bouw, we took care of the delivery and assembly of the steel construction for the Lidl in Eibergen. It was built on the site that was known as “the Eibergen hole”. We are very pleased with the end result of another beautiful Lidl. The new location was opened mid-April 2019.

read more
steel-construction

Canönde Erfstadt

For the company Canönde Tiefbau in Erftstadt we have built 3 halls on the new premises. The halls covered a total area of 1832 m2. Included in the order was the statics of the foundations and the steel structure. Delivery and installation of steel construction, facade cladding, roof seal including RWA systems as well as

read more
hall-construction

Boels Rental Bamberg

At the beginning of June we started with the foundations of the hall and the foundation work for the laundry room of the rental center. This was followed by the assembly of the steel structure and the prefabricated concrete base. The completion of the washing place followed. The complete coordination of the construction site is

read more
hall-construction

L’Osteria 3.0 Freestander Dortmund

In May 2019 we celebrated the opening of L’Osteria 3.0 Freestander in Dortmund. For this we have done the following; the roof truss construction with trapezoidal sheet metal covering. Substructure of the air conditioning with double-sided blinds of aluminum slats. At the front of the building we have built a nice terrace covering / landing

read more
stairs-and-fences

Breuninger Sachsenheim

On behalf of Ten Brinke Wohn- und Gewerbebau Doetinchem we have built various steel structures for a new logistics center in Sachsenheim. A three-storey T-shaped hall complex is planned. In this complex is an automated storage area for small parts, a goods handling area, staff space with about 170 office work surfaces and a marketing

read more
steel-construction

Anklaar Apeldoorn

Commissioned by Ten Brinke Bouw B.V we have built 3 large steel structures on top of the parking basements with connections to the houses and shops. We also had the Tapis Roulant Passage and the lift structure in our order. This project consists of commercial spaces with above 60 apartments spread over 4 building blocks

read more
steel-construction

Hornbach Duiven

At the Nieuwgraaf in Duiven, we have been commissioned by Ten Brinke Bouw Doetinchem to assemble the new steelconstruction (700 ton) of Hornbach Duiven. Subsequently, the assembly team will start assembling the hardware store and then the Drive inn. Here you can load the ordered materials immediately after purchase. The Hornbach will have a gross

read more
steel-construction

Toom Hof

Imetaal Industriebau commissioned us to assemble the steel structure for a new construction market in Hof Germany. The construction market has an area of approximately 5,400 m2. It also has a hot and cold hall of approximately 900 m2. (which will mainly be used for plants), as well as an outdoor area with approximately 1,200

read more
hall-construction

Kaffeerösterei Tempelmann Marl

In September 2016 we were commissioned by Ten Brinke Industrie- und Gewerbebau GmbH & Co. KG. to start with the delivery and assembly of the steel structure for the new Kaffeerösterei Tempelmann project in the northern Ruhr area in the Recklinghausen district in the 85,000-inhabitant town of Marl (NRW). This warehouse was taken into use

read more
steel-construction

Building 1931 Amsterdam

At the end of 2017 we started with the assembly of the steel construction and the channel plates of the ground floor at the former Citroën building (South). During the year 2018, the assembly was advanced floor by floor and we have now completed the assembly of the main structure, the channel plates and the

read more
customization

Ecodome

The sustainable steel construction for the Ecodome has been supplied by Imetaal Staalbouw. The Ecodome is an innovative construction with a diameter of 21 meters and a height of ten meters and is full of all kinds of technical and ‘natural’ concepts that have been developed by TU Delft, among others. On the Ecodome there

read more
customization

Orion College

The school building, a former pastry school, has been renovated and expanded with a new-build section containing a gym, extra teaching rooms and an outdoor area. The gym is housed in the cantilever that extends over the existing school building. The challenge with this project was the installation of the cantilever of approximately 8.5 meters

read more
customization
+31 88 5551300

Talen

Follow us on social media