Parkhaus Edeka Moers Fase 1
Description
Here some pictures of the assembly stand until wk 14 Parkhaus Edeka Moers
In week 15 the assembly axis H / A (axis 21 to 42) will be ready. We will also start finalizing the 3rd floor. Due to Good Friday, construction will also be mounted on Saturday 11 April.