Boels Rental Bamberg
Description
At the beginning of June we started with the foundations of the hall and the foundation work for the laundry room of the rental center. This was followed by the assembly of the steel structure and the prefabricated concrete base. The completion of the washing place followed. The complete coordination of the construction site is carried out by our project and construction manager. After completion of the facade and roofing, external windows and doors are installed. After the monolithic floor plate that we have laid has been hardened, we start with the finishing of the office, social and exhibition spaces.Recently we also successfully delivered Boels Rental in Remscheid.