Parkhaus Edeka Moers Fase 4
Description
Progress Parkhaus Moers until wk 21
We are now fully engaged in the assembly of beams, tubes and drive-on mats on the 6th floor.
By the end of this week we expect to be ready with this floor on axis 42 and are slightly ahead of schedule. However, we will need this lead with the 7th floor where the columns for the next floors will be added.